Carseldine
Complete Renovation of the lower level including removing load bearing walls to create an open plan Kitchen, Dining, Living and Lounge Area.Project Timeline
12 Weeks
Project Challenges
- Termite Damage was found upon strip out of the existing walls and ceilings, which we needed to replace- Structural Work required to support the upper level of the house, while keeping a lovely flat ceiling to the lower level
Project Highlights
- Kitchen- Tiled Floor
- Open Plan of lower level
Project Metrics
145m2 Lower Level Internal Renovationview Carseldine gallery