Hamilton
Previously raised Queenslander that we built in underneath. Lower Level included new bedroom, play room and entertaining area.Project Timeline
12 Weeks
Project Challenges
The ground level outside was level with the internal concrete slab creating a potential water ingress issue. We installed a concrete nib and waterproofed over the top including the whole lower level to ensure we created a detail to prevent ingress.Project Highlights
Entertaining AreaTiled Floor
VJ Walls & Ornate Cornice Profile
Project Metrics
50m2 of Lower Level30m2 of Entertaining Area
New Timber Windows & Doors
New Tiled Floor to lower level and entertaining area.
view Hamilton gallery